Context

Transport Scotland’s Building Capacity in the Safe System programme was designed to strengthen understanding and practical implementation of the Safe System approach among road safety practitioners and leaders across Scotland. 

The challenge was not simply to increase awareness of Safe System principles, but to support their translation into policy and practice. Transport Scotland wanted to understand how effectively the programme was being delivered, what was working well, where barriers remained, and how the work could be strengthened as it developed. The first phase therefore required an independent assessment of implementation, successes and challenges, while the later phase examined a significantly expanded programme of training and capacity-building activity. 

What ECMRS did

ECMRS provided an independent process evaluation across two phases of the programme. 

The first evaluation examined delivery of the initial Building Capacity in the Safe System project, including progress against agreed milestones, the experiences of Transport Scotland and the delivery partner Agilysis, and the key successes, barriers and lessons emerging from implementation. The evaluation drew on project documentation and structured stakeholder interviews, with qualitative data analysed thematically.

ECMRS was subsequently commissioned to evaluate Phase 2, which expanded the capacity-building programme through in-person and online training, stakeholder engagement and the development of a dedicated Safe System Manual. This second evaluation used a mixed-methods design combining stakeholder interviews, participant surveys and document review, allowing the evaluation to consider both programme implementation and participant outcomes. 

Project Information

Service:

Independent evaluation

Client:

Transport Scotland  

TS logo - Online-Digital

Project Period:

2024-2025

Focus:

Safe System, capacity building, training, road safety policy and practice

What the evaluation found

The first evaluation found that the programme had met its milestones while adapting flexibly to emerging needs. Strong leadership, communication and coordination supported delivery, while the programme generated high levels of enthusiasm among many practitioners and external experts. It also identified some of the practical challenges involved in building Safe System capability at scale, including stakeholder engagement, time and resource pressures, and the need to continue strengthening understanding of how Safe System principles translate into practice. 

Phase 2 showed how the programme had developed further. More than 500 people participated in the training, with demand exceeding expectations. Evaluation findings showed statistically significant improvements in participants’ Safe System knowledge, confidence and perceived relevance to their roles across both in-person and online formats. The two formats offered different strengths. The in-person programme was particularly valued for supporting deeper reflection, collaboration and systems thinking, while the online offer broadened access. 

The evaluation also highlighted areas for continued development, including stronger engagement with senior leaders, follow-up support to help translate learning into sustained practice, continued development of the Safe System Manual and opportunities for longer-term evaluation and peer learning. 

Why it mattered

The two evaluations provided Transport Scotland with independent evidence about both the delivery and emerging impact of its investment in Safe System capacity building. 

Rather than simply establishing whether activity had taken place, the work identified where the programme was delivering value, where further development was needed and how future investment could build on the progress already made. The findings also helped distinguish between different forms of capacity building rather than treating training as a single intervention. They provided evidence about the respective value of intensive in-person learning, more scalable online provision, leadership engagement and longer-term support for implementation. 